STOP PRESS

16 May 2013

Greenpeace has launched a legal challenge to EDF's proposed new nuclear plant at Hinkley Point in Somerset.

The environmental lobby group last week lodged an application for judicial review of the government's decision to grant consent for the project.

A spokesperson would not comment on the grounds for the challenge. However, it is expected to rest on the absence of "effective arrangements" for dealing with the nuclear waste that would be generated. Government plans for a waste disposal site in Cumbria fell through earlier this year after a local authority pulled out.

This judicial review comes hot on the heels of one from the National Trust for Ireland . It contends that the Irish people should have been consulted on the plans, given the risk of environmental damage to neighbouring countries in the event of a disaster.

Source: Utility Week


Hinkley C nuclear power station challenged by Irish National Trust

Government approval for the proposed new Hinkley C nuclear power station is being challenged in the High Court, by the National Trust for Ireland. More >>>
STOP PRESS

EDF delays Hinkley funding ‘until at least September'

17 May 2013

EDF will not make a final investment decision on its £10bn Hinkley nuclear plant project until at least September and is set to cut up to half the staff on the site in Somerset.

The French power company is expected to reach a deal with the government over what it can charge for the electricity from the power plant in Somerset - the so-called “strike price” - later this month, and had been expected to announce its investment decision soon after.

However, sources close to the project have said no decision is now expected till September at the earliest. One source said it would “probably” be nearer to Christmas.

As a result of the delayed investment decision, the main civils work, which is being undertaken by Laing O'Rourke and Bouygues, is set to start about six months behind EDF's last published schedule, which said that it would start at the beginning of 2014.

This was itself a year behind the firm's original indicative timetable, which said the civils work was due to start at the beginning of 2013.

In May 2012, EDF said the joint venture had been scheduled to start “large-scale earth-moving activities” at the start of 2013, but this is now not expected to start until spring 2014.

One key factor in the delay is understood to be the need for additional investors to come on board, after UK firm Centrica announced in February it would no longer be investing.

More >>>




Hinkley C Public Debate
Protester Crispin Aubrey says Process Undemocratic & Flawed



Stop Hinkley Logo

Page Updated 17-May-2013

 

Click here to obtain stickers


Don't Subsidise
Nuclear Power

The government plans to force everybody to pay for new nuclear power stations through their electricity bills, despite promising there would be no public subsidies.
More >>>


A new report, A Corruption of Governance, prepared for the Association for the Conservation of Energy and Unlock Democracy was presented to MPs and NGOs at the House of Commons. It exposes that the evidence given to Ministers and Parliament, promoting the use of nuclear power, was a false summary of the analysis carried out by government departments.
The report, supported by a cross party group of MPs, calls for the case for nuclear power to be re-examined in a parliamentary debate, so the true facts can be discussed. More >>>


Contact your MP
Support wind farms
Donate to support Stop Hinkley
Add www.stophinkley.org to your favourites
PETITIONS

PLEASE SIGN THESE PETITIONS.